Dept. of Trans. PROGRESS Serial No. Contract No. 16-328-15-48 12-0P4904 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 100% Location: Federal Project: 12-ORA-57 NONE Progress payment No. 003 Payment period ending: 11-20-16 R J NOBLE COMPANY PO BOX 620 ORANGE CA 92856 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 926,306.42 141,528.23 2. a. Extra Work 29,070.89 29,070.89 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 955,377.31 170,599.12 5. Mobilization 31,500.00 0.00 6. Total Work Completed 986,877.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 986,877.31 170,599.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 170,599.12