Dept. of Trans. PROGRESS Serial No. Contract No. 21-083-10-54 12-0P5204 PROGRESS PAYMENT VOUCHER %complete: %time: 27% 30% Location: Federal Project: 12-ORA-22-R9.4/L9.8 HSNH-X059(82) 12-ORA-57-10.9/11.4 Progress payment No. 004 Payment period ending: 03-20-21 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 316,167.10 155,444.20 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 129,890.10 0.00 4. Earned Subject to Retention 446,057.20 155,444.20 5. Mobilization 142,500.00 30,000.00 6. Total Work Completed 458,667.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 588,557.20 185,444.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 185,444.20