Dept. of Trans. PROGRESS Serial No. Contract No. 24-023-11-09 12-0P68U4 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 6% Location: Federal Project: 12-ORA-1-13.0/33.7 ACST-P00(682) Progress payment No. 003 Payment period ending: 01-20-24 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,012,175.03 426,248.94 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 34,262.01 34,262.01 4. Earned Subject to Retention 1,046,437.04 460,510.95 5. Mobilization 6. Total Work Completed 1,012,175.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,046,437.04 460,510.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 460,510.95