Dept. of Trans. PROGRESS Serial No. Contract No. 25-022-11-36 12-0P68U4 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 76% Location: Federal Project: 12-ORA-1-13.0/33.7 ACST-P00(682) Progress payment No. 016 Payment period ending: 01-20-25 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,846,280.01 1,045,398.00 2. a. Extra Work 869,779.30 77,373.73 b. Adustment Comp. 3. Materials on Hand 1,437,540.15 -263,657.13 4. Earned Subject to Retention 17,153,599.46 859,114.60 5. Mobilization 3,496,000.00 0.00 6. Total Work Completed 19,212,059.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -85,911.46 -85,911.46 c. Reduction after 95% Comp. 9. Total pay to Contractor 20,563,688.00 773,203.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 773,203.14