Dept. of Trans. PROGRESS Serial No. Contract No. 25-142-19-53 12-0P68U4 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 98% Location: Federal Project: 12-ORA-1-13.0/33.7 ACST-P00(682) Progress payment No. 020 Payment period ending: 05-20-25 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,003,395.43 3,851,335.39 2. a. Extra Work 985,810.69 58,465.53 b. Adustment Comp. 3. Materials on Hand 708,108.32 -455,339.38 4. Earned Subject to Retention 26,697,314.44 3,454,461.54 5. Mobilization 3,680,000.00 0.00 6. Total Work Completed 29,669,206.12 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 30,377,314.44 3,454,461.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,454,461.54