Dept. of Trans. PROGRESS Serial No. Contract No. 25-356-14-42 12-0P69U4 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 94% Location: Federal Project: 12-ORA-1-5.5/7.9 ACST-P001(680) Progress payment No. 027 Payment period ending: 12-20-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,162,987.42 205,847.70 2. a. Extra Work 285,762.94 25,587.99 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 14,448,750.36 231,435.69 5. Mobilization 700,000.00 0.00 6. Total Work Completed 15,148,750.36 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,148,750.36 241,435.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 241,435.69