Dept. of Trans. PROGRESS Serial No. Contract No. 23-081-09-08 12-0P7004 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 58% Location: Federal Project: 12-ORA-5-3.3/3.3 NONE Progress payment No. 021 Payment period ending: 03-20-23 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,433,324.10 13,640.00 2. a. Extra Work 120,388.70 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,553,712.80 13,640.00 5. Mobilization 196,658.00 0.00 6. Total Work Completed 2,750,370.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,750,370.80 13,640.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,640.00