Dept. of Trans. PROGRESS Serial No. Contract No. 20-170-11-01 12-0P7204 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 92% Location: Federal Project: 12-ORA-55-17.2/17.2 HSNH-X059(78) Progress payment No. 013 Payment period ending: 06-20-20 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 726,657.94 257,831.49 2. a. Extra Work 59,585.39 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 786,243.33 257,831.49 5. Mobilization 70,000.00 0.00 6. Total Work Completed 856,243.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 856,243.33 257,831.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 257,831.49