Dept. of Trans. PROGRESS Serial No. Contract No. 21-323-10-59 12-0P9104 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 49% Location: Federal Project: 12-ORA-5-36.8/38.5 NONE Progress payment No. 003 Payment period ending: 11-20-21 ACCU CONSTRUCTION INC 2098 S GRAND AVE #A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 459,210.62 302,460.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 459,210.62 302,460.00 5. Mobilization 10,000.00 500.00 6. Total Work Completed 469,210.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 469,210.62 302,960.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 302,960.00