Dept. of Trans. PROGRESS Serial No. Contract No. 22-356-09-11 12-0P9204 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 22% Location: Federal Project: 12-ORA-5-38.5/41.6 ACIM-052(29) Progress payment No. 006 Payment period ending: 12-20-22 ACCU CONSTRUCTION INC 14751 PLAZA DRIVE #L TUSTIN CA 92780 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 697,044.90 21,600.20 2. a. Extra Work 1,408.58 1,308.58 b. Adustment Comp. 3. Materials on Hand 84,266.97 0.00 4. Earned Subject to Retention 782,720.45 22,908.78 5. Mobilization 30,000.00 0.00 6. Total Work Completed 728,453.48 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 802,720.45 22,908.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,908.78