Dept. of Trans. PROGRESS Serial No. Contract No. 18-023-14-13 12-0Q0304 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 58% Location: Federal Project: 12-ORA-39-0.0/12.9 NONE Progress payment No. 002 Payment period ending: 01-20-18 INTEGRITY LANDSCAPE AND CONCRETE 313 E ORANGE GROVE BLVD #290 PASADENA CA 91104 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,925.85 31,275.85 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 33,925.85 31,275.85 5. Mobilization 19,074.15 19,074.15 6. Total Work Completed 53,000.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 53,000.00 50,350.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,350.00