Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-09-26 12-0Q1104 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 35% Location: Federal Project: 12-ORA-57-15.6/22.5 ACNH-P057(65) Progress payment No. 002 Payment period ending: 09-20-17 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 820,797.23 502,184.68 2. a. Extra Work 2,174.98 2,174.98 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 822,972.21 504,359.66 5. Mobilization 285,000.00 60,000.00 6. Total Work Completed 1,107,972.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,107,972.21 564,359.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 564,359.66