Dept. of Trans. PROGRESS Serial No. Contract No. 19-148-10-41 12-0Q1304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 52% Location: Federal Project: 12-ORA-261-0.0/0.3 SSTG-P261(3) Progress payment No. 003 Payment period ending: 05-20-19 GENUINE ENGINEERING INC 13306 INDIAN BOW CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 283,627.00 84,009.95 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 283,627.00 84,009.95 5. Mobilization 37,500.00 0.00 6. Total Work Completed 321,127.00 7. Deductions -5,749.80 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 315,377.20 84,009.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,009.95