Dept. of Trans. PROGRESS Serial No. Contract No. 20-357-12-57 12-0Q2804 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 19% Location: Federal Project: 12-ORA-1-27.0/29.9 SNHG-P001(670) Progress payment No. 004 Payment period ending: 12-20-20 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 466,117.00 14,610.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 466,117.00 14,610.00 5. Mobilization 33,000.00 0.00 6. Total Work Completed 499,117.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 499,117.00 14,610.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,610.00