Dept. of Trans. PROGRESS Serial No. Contract No. 22-025-10-09 12-0Q3104 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 4% Location: Federal Project: 12-ORA-91-R1.8/R3.4 SNHG-P091(149) Progress payment No. 002 Payment period ending: 01-20-22 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 90,265.00 90,265.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 84,266.97 0.00 4. Earned Subject to Retention 174,531.97 90,265.00 5. Mobilization 25,000.00 25,000.00 6. Total Work Completed 115,265.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 199,531.97 115,265.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,265.00