Dept. of Trans. PROGRESS Serial No. Contract No. 22-054-10-34 12-0Q3104 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 16% Location: Federal Project: 12-ORA-91-R1.8/R3.4 SNHG-P091(149) Progress payment No. 003 Payment period ending: 02-20-22 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 195,201.00 104,936.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 77,241.97 -7,025.00 4. Earned Subject to Retention 272,442.97 97,911.00 5. Mobilization 37,500.00 12,500.00 6. Total Work Completed 232,701.00 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 299,942.97 100,411.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,411.00