Dept. of Trans. PROGRESS Serial No. Contract No. 19-113-11-18 12-0Q4604 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 16% Location: Federal Project: 12-ORA-55-17.0/17.0 NONE Progress payment No. 006 Payment period ending: 04-20-19 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 607,329.50 200,346.64 2. a. Extra Work 55,046.79 6,618.94 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 662,376.29 206,965.58 5. Mobilization 44,000.00 2,200.00 6. Total Work Completed 706,376.29 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 706,376.29 209,165.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 209,165.58