Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 20-184-07-25 12-0Q5804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-5-2.7/17.1 NONE Progress payment No. 003 Payment period ending: 06-12-20 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 485,233.00 249,573.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 485,233.00 249,573.00 5. Mobilization 12,000.00 600.00 6. Total Work Completed 497,233.00 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 487,233.00 250,173.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 250,173.00