Dept. of Trans. PROGRESS Serial No. Contract No. 22-049-14-09 12-0Q6504 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 49% Location: Federal Project: 12-ORA-22-1.2/1.2 SNHG-P022(27) Progress payment No. 004 Payment period ending: 02-20-22 INTERNATIONAL LINE BUILDERS, INC. 3955 TEMESCAL CYN RD CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,535.15 31,775.05 2. a. Extra Work 4,737.73 4,737.73 b. Adustment Comp. 3. Materials on Hand 56,130.78 56,130.78 4. Earned Subject to Retention 117,403.66 92,643.56 5. Mobilization 33,440.00 15,840.00 6. Total Work Completed 94,712.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 150,843.66 108,483.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,483.56