Dept. of Trans. PROGRESS Serial No. Contract No. 21-083-15-37 12-0Q8104 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 71% Location: Federal Project: 12-ORA-241-23.1/23.1 HSST-P241(7) Progress payment No. 007 Payment period ending: 03-20-21 RSB GROUP INC 20331 LAKE FOREST DR #C-13 LAKE FOREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 784,394.39 41,429.00 2. a. Extra Work 37,026.90 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 821,421.29 41,429.00 5. Mobilization 4,000.00 0.00 6. Total Work Completed 825,421.29 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 825,421.29 41,429.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,429.00