Dept. of Trans. PROGRESS Serial No. Contract No. 22-355-13-09 12-0Q8204 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 89% Location: Federal Project: 12-ORA-5-30.3/31.4 HSIM-052(28) Progress payment No. 009 Payment period ending: 12-20-22 R J NOBLE COMPANY 15505 E LINCOLN AVE ORANGE CA 92865 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,872,489.72 149,634.15 2. a. Extra Work 22,603.29 13,579.39 b. Adustment Comp. 231,397.29 55,530.28 3. Materials on Hand 4. Earned Subject to Retention 3,126,490.30 218,743.82 5. Mobilization 130,000.00 0.00 6. Total Work Completed 3,256,490.30 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,256,490.30 228,743.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 228,743.82