Dept. of Trans. PROGRESS Serial No. Contract No. 23-143-10-42 12-0Q8304 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 87% Location: Federal Project: 12-ORA-1-20.4/23.7 SNHG-P001(677) Progress payment No. 008 Payment period ending: 05-20-23 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 918,693.50 167,190.50 2. a. Extra Work 23,168.79 0.00 b. Adustment Comp. 3. Materials on Hand 11,190.38 0.00 4. Earned Subject to Retention 953,052.67 167,190.50 5. Mobilization 39,393.50 0.00 6. Total Work Completed 981,255.79 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 992,446.17 167,190.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 167,190.50