Dept. of Trans. SEMI-FINAL Serial No. Contract No. 23-010-14-18 12-0Q8504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-5-34.5/37.4 HSIM-052(22) Progress payment No. 016 Payment period ending: 07-07-22 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,433,204.80 72,125.00 2. a. Extra Work 54,862.85 0.00 b. Adustment Comp. -901.26 -901.26 3. Materials on Hand 4. Earned Subject to Retention 5,487,166.39 71,223.74 5. Mobilization 45,000.00 0.00 6. Total Work Completed 5,532,166.39 7. Deductions -20,000.00 42,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,512,166.39 113,223.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 113,223.74