Dept. of Trans. PROGRESS Serial No. Contract No. 17-360-07-58 12-0Q8604 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 31% Location: Federal Project: 12-ORA-57-11.0/19.6 NONE Progress payment No. 004 Payment period ending: 12-20-17 AUTOBAHN CONSTRUCTION, INC PO BOX 11238 SANTA ANA CA 92711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,681,278.71 862,228.71 2. a. Extra Work 30,085.21 14,220.55 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,711,363.92 876,449.26 5. Mobilization 251,750.00 53,000.00 6. Total Work Completed 1,963,113.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,963,113.92 929,449.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 929,449.26