Dept. of Trans. PROGRESS Serial No. Contract No. 23-053-12-17 12-0Q9304 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 29% Location: Federal Project: 12-ORA-5-5.8/30.3 ACNH-X059(85) Progress payment No. 006 Payment period ending: 02-20-23 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,735,176.56 699,811.32 2. a. Extra Work 11,261.18 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -243,150.00 4. Earned Subject to Retention 1,746,437.74 456,661.32 5. Mobilization 1,162,500.00 387,500.00 6. Total Work Completed 2,908,937.74 7. Deductions -49,048.94 -16,349.65 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,859,888.80 827,811.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 827,811.67