Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 24-029-11-18 12-0Q9304 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 82% Location: Federal Project: 12-ORA-5-5.8/30.3 ACNH-X059(85) Progress payment No. 018 Payment period ending: 01-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,894,406.22 0.00 2. a. Extra Work 95,114.96 0.00 b. Adustment Comp. 303,983.94 0.00 3. Materials on Hand 300,522.00 300,522.00 4. Earned Subject to Retention 9,594,027.12 300,522.00 5. Mobilization 1,550,000.00 0.00 6. Total Work Completed 10,843,505.12 7. Deductions -65,398.59 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,078,628.53 300,522.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 300,522.00