Dept. of Trans. PROGRESS Serial No. Contract No. 24-326-13-01 12-0Q9304 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 100% Location: Federal Project: 12-ORA-5-5.8/30.3 ACNH-X059(85) Progress payment No. 026 Payment period ending: 11-20-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,083,435.77 249,395.00 2. a. Extra Work 163,195.61 33,815.13 b. Adustment Comp. 303,983.94 0.00 3. Materials on Hand 269,600.00 7,174.00 4. Earned Subject to Retention 10,820,215.32 290,384.13 5. Mobilization 1,550,000.00 0.00 6. Total Work Completed 12,100,615.32 7. Deductions -65,398.59 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 27,515.05 c. Reduction after 95% Comp. 9. Total pay to Contractor 12,304,816.73 317,899.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 317,899.18