Dept. of Trans. PROGRESS Serial No. Contract No. 24-199-14-09 12-0Q9704 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 35% Location: Federal Project: 12-ORA-405-0.2/11.4 ACIM-4052(3) Progress payment No. 011 Payment period ending: 07-20-24 GUY F ATKINSON CONSTRUCTION LLC 18201 VON KARMAN AVE #800 IRVINE CA 92612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,059,561.25 3,014,716.00 2. a. Extra Work 64,181.95 26,250.60 b. Adustment Comp. -54,727.16 2,975.98 3. Materials on Hand 4. Earned Subject to Retention 34,069,016.04 3,043,942.58 5. Mobilization 16,200,000.00 0.00 6. Total Work Completed 50,269,016.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 50,269,016.04 3,043,942.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,043,942.58