Dept. of Trans. PROGRESS Serial No. Contract No. 24-359-13-40 12-0Q9704 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 52% Location: Federal Project: 12-ORA-405-0.2/11.4 ACIM-4052(3) Progress payment No. 016 Payment period ending: 12-20-24 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,534,053.13 4,225,891.25 2. a. Extra Work 154,907.67 1,366.20 b. Adustment Comp. -469,497.84 0.00 3. Materials on Hand 1,024,286.27 171,499.58 4. Earned Subject to Retention 54,243,749.23 4,398,757.03 5. Mobilization 20,520,000.00 0.00 6. Total Work Completed 73,739,462.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 74,763,749.23 4,398,757.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,398,757.03