Dept. of Trans. PROGRESS Serial No. Contract No. 25-027-07-14 12-0Q9704 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 64% Location: Federal Project: 12-ORA-405-0.2/11.4 ACIM-4052(3) Progress payment No. 017 Payment period ending: 01-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 57,834,822.25 4,300,769.13 2. a. Extra Work 273,983.41 119,075.74 b. Adustment Comp. -469,497.84 0.00 3. Materials on Hand 1,024,286.27 0.00 4. Earned Subject to Retention 58,663,594.09 4,419,844.87 5. Mobilization 20,520,000.00 0.00 6. Total Work Completed 78,159,307.82 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 79,178,594.09 4,414,844.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,414,844.87