Dept. of Trans. PROGRESS Serial No. Contract No. 25-051-09-38 12-0Q9704 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 57% Location: Federal Project: 12-ORA-405-0.2/11.4 ACIM-4052(3) Progress payment No. 018 Payment period ending: 02-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 63,382,121.38 5,547,299.13 2. a. Extra Work 310,336.21 36,352.80 b. Adustment Comp. -469,497.84 0.00 3. Materials on Hand 1,103,141.94 78,855.67 4. Earned Subject to Retention 64,326,101.69 5,662,507.60 5. Mobilization 20,520,000.00 0.00 6. Total Work Completed 83,742,959.75 7. Deductions -25,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 84,821,101.69 5,642,507.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,642,507.60