Dept. of Trans. PROGRESS Serial No. Contract No. 25-112-08-31 12-0Q9704 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 62% Location: Federal Project: 12-ORA-405-0.2/11.4 ACIM-4052(3) Progress payment No. 020 Payment period ending: 04-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 73,124,454.88 7,077,261.00 2. a. Extra Work 311,686.21 1,350.00 b. Adustment Comp. -469,497.84 0.00 3. Materials on Hand 3,178,188.06 229,996.04 4. Earned Subject to Retention 76,144,831.31 7,308,607.04 5. Mobilization 20,520,000.00 0.00 6. Total Work Completed 93,486,643.25 7. Deductions -25,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 96,639,831.31 7,308,607.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,308,607.04