Dept. of Trans. PROGRESS Serial No. Contract No. 25-203-12-58 12-0Q9704 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 72% Location: Federal Project: 12-ORA-405-0.2/11.4 ACIM-4052(3) Progress payment No. 023 Payment period ending: 07-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,591,365.00 10,199,883.88 2. a. Extra Work 418,619.76 47,505.97 b. Adustment Comp. -469,497.84 0.00 3. Materials on Hand 3,443,861.71 0.00 4. Earned Subject to Retention 103,984,348.63 10,247,389.85 5. Mobilization 20,520,000.00 0.00 6. Total Work Completed 121,060,486.92 7. Deductions -25,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 124,479,348.63 10,247,389.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,247,389.85