Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-15-42 12-0Q9704 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 82% Location: Federal Project: 12-ORA-405-0.2/11.4 ACIM-4052(3) Progress payment No. 026 Payment period ending: 10-20-25 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 127,439,752.75 8,463,339.13 2. a. Extra Work 860,465.98 321,051.11 b. Adustment Comp. -1,068,915.81 -599,417.97 3. Materials on Hand 3,443,861.71 0.00 4. Earned Subject to Retention 130,675,164.63 8,184,972.27 5. Mobilization 21,600,000.00 0.00 6. Total Work Completed 148,831,302.92 7. Deductions -25,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 152,250,164.63 8,184,972.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,184,972.27