Dept. of Trans. PROGRESS Serial No. Contract No. 26-054-12-19 12-0Q9704 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 90% Location: Federal Project: 12-ORA-405-0.2/11.4 ACIM-4052(3) Progress payment No. 030 Payment period ending: 02-20-26 GUY F ATKINSON CONSTRUCTION LLC 611 ANTON BLVD #1100 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 154,357,384.63 7,945,112.50 2. a. Extra Work 1,215,886.47 137,106.21 b. Adustment Comp. -1,153,962.25 0.00 3. Materials on Hand 3,830,843.76 0.00 4. Earned Subject to Retention 158,250,152.61 8,082,218.71 5. Mobilization 21,600,000.00 0.00 6. Total Work Completed 176,019,308.85 7. Deductions -133,100.00 -108,100.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 179,717,052.61 7,974,118.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,974,118.71