Dept. of Trans. PROGRESS Serial No. Contract No. 18-143-09-07 12-0R0704 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 26% Location: Federal Project: 12-ORA-5-0.0/44.4 NONE Progress payment No. 002 Payment period ending: 05-20-18 BC RENTALS INC DBA BC TRAFFIC SPECIALIST 638 W. SOUTHERN AVE ORANGE CA 92865 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 283,165.10 281,290.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 283,165.10 281,290.10 5. Mobilization 175,000.00 175,000.00 6. Total Work Completed 458,165.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 458,165.10 456,290.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 456,290.10