Dept. of Trans. PROGRESS Serial No. Contract No. 23-332-12-42 12-0R1504 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 9% Location: Federal Project: 12-ORA-55-13.7/13.7 HSNH-P055(65) Progress payment No. 001 Payment period ending: 11-20-23 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,154.00 193,154.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 193,154.00 193,154.00 5. Mobilization 27,918.00 27,918.00 6. Total Work Completed 221,072.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 221,072.00 221,072.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 221,072.00