Dept. of Trans. PROGRESS Serial No. Contract No. 24-082-09-55 12-0R1804 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 71% Location: Federal Project: 12-ORA-90-0.9/3.6 HSNH-P090(18) Progress payment No. 009 Payment period ending: 03-20-24 CALPROMAX ENGINEERING INC 650 N ROSE DRIVE #186 PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 659,696.00 59,972.00 2. a. Extra Work 45,663.74 3,260.40 b. Adustment Comp. 14,239.68 0.00 3. Materials on Hand 4. Earned Subject to Retention 719,599.42 63,232.40 5. Mobilization 118,750.00 0.00 6. Total Work Completed 838,349.42 7. Deductions -20,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 818,349.42 53,232.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,232.40