Dept. of Trans. PROGRESS Serial No. Contract No. 19-204-11-30 12-0R2704 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 41% Location: Federal Project: 12-ORA-5-21.4/25.0 NONE Progress payment No. 002 Payment period ending: 07-20-19 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 262,879.00 199,065.00 2. a. Extra Work 10,146.00 10,146.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 273,025.00 209,211.00 5. Mobilization 104,150.00 104,150.00 6. Total Work Completed 377,175.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 377,175.00 313,361.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 313,361.00