Dept. of Trans. FINAL Serial No. Contract No. 24-108-10-51 12-0R2904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 12-ORA-22-R5.5/5.5 HSNH-P022(29) Progress payment No. 009 Payment period ending: 01-04-24 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 742,965.10 6,415.00 2. a. Extra Work 14,299.40 14,299.40 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 757,264.50 20,714.40 5. Mobilization 35,000.00 0.00 6. Total Work Completed 792,264.50 7. Deductions 0.00 30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 792,264.50 50,714.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,714.40