Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-12-50 12-0R3114 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 18% Location: Federal Project: 12-LA-91-R20.6/R20.7 ACNH-P091(159) 12-ORA-91-R0.0/4.8 Progress payment No. 006 Payment period ending: 10-20-25 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,777,882.46 1,554,150.94 2. a. Extra Work 22,018.50 22,018.50 b. Adustment Comp. 3. Materials on Hand 372,410.54 144,895.88 4. Earned Subject to Retention 12,172,311.50 1,721,065.32 5. Mobilization 4,061,250.00 0.00 6. Total Work Completed 15,861,150.96 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,233,561.50 1,721,065.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,721,065.32