Dept. of Trans. PROGRESS Serial No. Contract No. 26-021-13-26 12-0R3114 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 27% Location: Federal Project: 12-LA-91-R20.6/R20.7 ACNH-P091(159) 12-ORA-91-R0.0/4.8 Progress payment No. 009 Payment period ending: 01-20-26 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,166,983.85 366,287.79 2. a. Extra Work 494,424.12 247,541.47 b. Adustment Comp. 3. Materials on Hand 429,403.33 -30,810.33 4. Earned Subject to Retention 16,090,811.30 583,018.93 5. Mobilization 4,061,250.00 0.00 6. Total Work Completed 19,722,657.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,152,061.30 583,018.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 583,018.93