Dept. of Trans. PROGRESS Serial No. Contract No. 26-112-11-04 12-0R3114 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 36% Location: Federal Project: 12-LA-91-R20.6/R20.7 ACNH-P091(159) 12-ORA-91-R0.0/4.8 Progress payment No. 012 Payment period ending: 04-20-26 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,611,866.26 1,231,841.59 2. a. Extra Work 685,779.11 191,354.99 b. Adustment Comp. 3. Materials on Hand 753,111.30 327,832.61 4. Earned Subject to Retention 20,050,756.67 1,751,029.19 5. Mobilization 4,061,250.00 0.00 6. Total Work Completed 23,358,895.37 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,112,006.67 1,751,029.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,751,029.19