Dept. of Trans. PROGRESS Serial No. Contract No. 25-199-15-22 12-0R3154 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 10% Location: Federal Project: 12-ORA-91-R10.8/R18.9 ACNH-P091(157) Progress payment No. 003 Payment period ending: 07-20-25 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 764,955.00 328,795.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 151,457.00 151,457.00 4. Earned Subject to Retention 916,412.00 480,252.00 5. Mobilization 515,560.50 0.00 6. Total Work Completed 1,280,515.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,431,972.50 480,252.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 480,252.00