Dept. of Trans. PROGRESS Serial No. Contract No. 26-083-11-56 12-0R32U4 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 24% Location: Federal Project: 12-ORA-55-0.2/R17.8 ACNH-P055(67) Progress payment No. 011 Payment period ending: 03-20-26 R J NOBLE COMPANY PO BOX 620 ORANGE CA 92856 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,140,577.58 4,936,270.97 2. a. Extra Work 1,008,801.21 100,461.69 b. Adustment Comp. 136,986.30 136,986.30 3. Materials on Hand 1,667,759.00 247,711.00 4. Earned Subject to Retention 22,954,124.09 5,421,429.96 5. Mobilization 6,650,000.00 1,400,000.00 6. Total Work Completed 27,936,365.09 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,604,124.09 6,821,429.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,821,429.96