Dept. of Trans. PROGRESS Serial No. Contract No. 20-170-09-33 12-0R5204 PROGRESS PAYMENT VOUCHER %complete: %time: 24% 43% Location: Federal Project: 12-ORA-241-16.0/38.8 NONE Progress payment No. 003 Payment period ending: 06-20-20 SPECTRUM CONSTRUCTION GROUP INC 16 GOODYEAR #140 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 354,274.68 229,038.58 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 354,274.68 229,038.58 5. Mobilization 104,500.00 49,500.00 6. Total Work Completed 458,774.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 458,774.68 278,538.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 278,538.58