Dept. of Trans. PROGRESS Serial No. Contract No. 20-203-11-01 12-0R5204 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 67% Location: Federal Project: 12-ORA-241-16.0/38.8 NONE Progress payment No. 004 Payment period ending: 07-20-20 SPECTRUM CONSTRUCTION GROUP INC 16 GOODYEAR #140 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 521,211.54 166,936.86 2. a. Extra Work 54,711.27 54,711.27 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 575,922.81 221,648.13 5. Mobilization 104,500.00 0.00 6. Total Work Completed 680,422.81 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 680,422.81 221,648.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 221,648.13