Dept. of Trans. PROGRESS Serial No. Contract No. 20-170-09-54 12-0R5404 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 0% Location: Federal Project: 12-ORA-5-1.6/33.1 NONE Progress payment No. 001 Payment period ending: 06-20-20 VELARDE CONCRETE CONSTRUCTION INC 523 S. BRAND BLVD, #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,722.21 52,722.21 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 52,722.21 52,722.21 5. Mobilization 6. Total Work Completed 52,722.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 52,722.21 52,722.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,722.21