Dept. of Trans. PROGRESS Serial No. Contract No. 24-206-15-50 12-0R5604 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 34% Location: Federal Project: 12-VAR-55-R5.5/R17.8 ACNH-X059(87) Progress payment No. 012 Payment period ending: 07-20-24 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,219,505.00 2,012,883.90 2. a. Extra Work 267,207.83 0.00 b. Adustment Comp. 150,000.00 0.00 3. Materials on Hand 460,020.07 31,694.95 4. Earned Subject to Retention 17,096,732.90 2,044,578.85 5. Mobilization 3,325,000.00 0.00 6. Total Work Completed 19,961,712.83 7. Deductions -27,600.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,394,132.90 2,044,578.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,044,578.85