Dept. of Trans. PROGRESS Serial No. Contract No. 24-261-15-12 12-0R5604 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 41% Location: Federal Project: 12-VAR-55-R5.5/R17.8 ACNH-X059(87) Progress payment No. 014 Payment period ending: 09-20-24 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,995,686.90 638,682.20 2. a. Extra Work 269,372.67 2,164.84 b. Adustment Comp. 132,061.04 0.00 3. Materials on Hand 420,615.24 -12,879.64 4. Earned Subject to Retention 18,817,735.85 627,967.40 5. Mobilization 3,500,000.00 175,000.00 6. Total Work Completed 21,897,120.61 7. Deductions -27,600.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,290,135.85 802,967.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 802,967.40